Politics

Hanford safety issues dog new plant

Questions surround the construction of a glassification plant. Will a cleanup plan create new nuclear dangers?

Hanford safety issues dog new plant
Sponsorship

by

John Stang

Questions surround the construction of a glassification plant. Will a cleanup plan create new nuclear dangers?

A huge $12 billion complex to turn highly  radioactive sludges into benign glass is the biggest project yet to clean up the radioactive wastes of Hanford nuclear reservation next to the Tri-Cities. But conflicting  forces raise the question of whether the project is being done safely.

Two major considerations have been tugging the project in opposite  directions — getting the project done on time versus making sure it will  work safely. The people in charge of the project contend both concerns  are being taken care of simultaneously. But  internal critics, working for the same federal agency and same project  contractor, say design problems are being deliberately and unsafely  ignored to keep the project on schedule.

Since Hanford's cleanup efforts began in 1989, this tension has  existed. The site frequently receives criticism for dawdling on cleanup;  and the site frequently receives criticism for cutting corners in  trying to keep to the latest schedule for the often-delayed cleanup.

Another factor may be in play. Hanford's critics point to the regular  turnover in Hanford's top leaders in Richland and in Washington D.C.   They argue that  a top official might spend two or three  years on a  project and move elsewhere, just long enough to record doing good things on a  resume without having to live with whether the glassification project  will work as advertised when it goes online in 2019.

Hanford's master plan is to build a $12.3 billion complex to mix  those  wastes with liquid glass to create glass cylinders capable of  holding in  the radioactivity for 10,000 years. This troubled  glassification project has a history of delays and cost increases. The  price tag of $4 billion in 2002 grew  $12.3 billion by  early 2006 and has stayed steady since. The original  start-up date of  1999 has been delayed to 2007, then to  2011 and now to  2019.

"Everyone is worried in the moment about their  careers and jobs — and 2019 (when the glassification plant becomes  active) is nine years away. Whoever you are talking to today, chances  are they won't be there two years from now," said Tom Carpenter,  director  of Seattle-based watchdog organization Hanford Challenge in a  late 2010 interview.

"It's the game of deny and delay," said Walt Tamosaitis, a veteran  Hanford engineering team leader who used to be in charge of making sure a  key component of the glassification plant would work as planned. The  deadline to fix design problems in that key component, a pretreatment  plant to prepares wastes for glassification, was June 30, 2010.   the  U.S. Department of Energy was supposed to pay Bechtel National Inc. and  its lead subcontractor URS Corp. $5 million for meeting that deadline.  At that time, DOE, Bechtel and URS agreed that the deadline was met,  justifying the $5 million payment.

But in the months leading up to the deadline, Tamosaitis argued that  the engineering problems  were not adequately addressed. He still  contends they have not been fixed. And on July 2, 2010, without warning,  URS transferred Tamosaitis to a minor procurement job. Tamosaitis has  filed a lawsuit in Benton County Superior Court against Bechtel and URS,  alleging that he was transferred because he was raising legitimate  concerns that would have ensured the June 30, 2010 would not be met.   DOE and Bechtel say he was routinely transferred because his team's work  was done.

Tamosaitis' lawsuit alleged that Russo and William Gay, URS's   assistant manager for the glassification project,  pushed hard to get an issue around the plant's   mixing of the wastes resolved by June 30, 2010 in order to get the $5   million award fee. Tamosaitis charged that the pair pushed for weakening   the standards which the mixing segment had to meet. Tamosaitis' lawsuit alleged that between February and June 2010, Gay   repeatedly mentioned how not  meeting the June 30 deadline could hurt   careers and compensation. The lawsuit said: "On one or more occasions,   Gay stated, 'If (the mixing issue ) doesn't close, I'll be selling   Amway in Tijuana.' "

Over the last several months, DOE and Bechtel declined to let the   appropriate officials to answer press questions, preferring to let   spokespeople to address questions. The spokespeople said the design   problems are either resolved or plans have been mapped out to tackle the   unresolved engineering questions.

In the glassification complex, radioactive wastes will be pumped from  the 177 tanks to the first stage of the glassification complex, which  will be the 12-story, 540-foot-long, 215-foot-wide "pretreatment"  building. There, the radioactive wastes will be mixed and separated into  milkshake-like slurries to go to neighboring radioactive waste  glassification buildlngs. Starting in 2019, almost all of the  pretreatment building's insides will be too radioactive for people to  enter.

Consequently, the pretreatment building's mixing tanks and pipes  won't have moveable parts. Mixing will be done by air pumps that act  like turkey basters in sucking air out of and blowing it into the tanks.  If something has to be be replaced, an entire section of equipment will  be removed by remote control on tracks to the building's huge central  corridor — also too radioactive for people to enter.

Tamosaitis was in charge of making sure the 38 mixing tanks will work  as desired. Issues included getting the solids small enough and spread  out enough so they don't clog pipes or cause criticalities. All sides in  this controversy  agreed that criticalities are rare, but are huge  problems when they occur.  Meanwhile, the clogging can slow down how  fast wastes are mixed, which could extend the amount of time that  Hanford needs to glassify the wastes.

Other mixing issues include inevitable burps of hydrogen gas. How big  will they be? Are explosions possible? Can they catch on fire?  Will  they bend the pipes and tanks enough that replacements will be needed?   Will the chemicals react and bind as needed so the slurries can be later  glassified? Will solids or sludges collect in the pretreatment plant's  32 tanks, possibly increasing the likelihood of a criticality occurring?  Will the mixtures leave the pretreatment building in the proper  chemical and physical conditions?

The stakes are high. If the mixing tanks don't work as designed, the  pretreatment plant will have to be redesigned and rebuilt. That could  translate to billions of extra dollars and some extra years before  glassification could start again. But other stakes are involved. Falling  behind the design and construction schedules lead to DOE paying  millions of dollars less to Bechtel and URS.

When  contacted recently, DOE spokeswoman Lori Gamache said: "The department has  established strict nuclear safety criteria for the facility that must be  met before any operations can begin. We will not allow the (tanks) to  be installed until the results from large-scale testing have shown the  the (tank) designs will safely and effectively handle the wastes at the  site." Bechtel echoed that statement.

Tamosaitis contends the engineering questions are still unresolved. Several other experts, including Donald Alexander of the Department of Energy's nuclear safety division, agree with him, and the Defense Nuclear Safety Board has called for increased precautions around the transfer of materials to the glassification plant.

On July 1, 2010, the Consortium for Risk Evaluation and Stakeholder  Participation — an independent technical review team under contract to  DOE — released a report that found uncertainties with the pulse-jet  mixer performances in the pretreatment plant and voiced several other  safety concerns including the need for full-scale testing. Another  concern was that different wastes in different mixtures exist in those  of the 177 tanks that would be pumped into the pretreatment plant. And  no  one has a good handle on the exact chemical compositions in those  tanks, and that knowledge could be vital for the pretreatment process to  work.

One disputed issue is whether Hanford correctly extrapolated from a  tabletop mixing test to a full-sized set of equipment. That dispute  shows up in a May 20, 2010  email from David Dickey to Tamosaitis.  Dickey is the head of MixTech Inc., an Ohio-based chemical engineering  consulting firm that specializes in chemical  mixing issues, and which  was hired by the project's contractors. Dickey wrote: "The use of the  0.18 exponent for scale-up would be considered by me to be criminally  negligent with respect to the design of a nuclear waste processing  plant. Is this response worded strong enough?" When  chemical engineers extrapolate from small-model tests to a full-sized  pulse-jet mixing tank in the pretreatment plant, a scaling factor of  0.33 is an industry standard.

DOE and Bechtel spokespeople said that future tests are being planning  to address scaling up the calculations from a tabletop size to a  full-size mixing tank. Large-scale tests will be conducted before  installing the tanks will be locked in, they said.

John Stang

By John Stang

John Stang is a freelance writer who often covers state government and the environment. He can be reached on email at johnstang_8@hotmail.com and on Twitter at @johnstang_8